Project Report
| May 31, 2017
Provide housing for 298 flood victims in India
By j Ranga Rao | Project Leader
![Slab work is being done]()
Slab work is being done
This project "To Provide Housing for 298 Flood Victims in India" has been successfully implementing in the Avanigadda and Nagayalanka Mandals of Krishna District in Andhra Pradesh, India. Since the villagers of these two mandals are severely affected during the floods, ASSIST staff are motivating to the flood victims and bringing them into normal life. ASSIST has taken the initiative to build new houses for the flood victims and construction of new houses to these flood victims is underway with the support of generous donors through GlobalGiving.
The following information shows the status of the Construction of 298 Houses to the Flood Victims in Avanigadda and Nagayalanka Mandals in India.
- Houses fully completed with sanitary latrine– 17
- Houses completed but not the latrine – 17
- Houses completed but flooring yet to be done– 50
- Houses with roof slab completed – 56
- Houses come up to roof level – 11
- Houses come up to lintel level – 8
- Houses come up to window sill level – 9
- Houses come up to Basement level – 15
- Houses not started yet -113
We look forward to the continued support from the generous donors in order to complete the rest of the houses.
![House construction is in progress]()
House construction is in progress
![House been built up to slab level]()
House been built up to slab level
![Construction is in progress]()
Construction is in progress
Feb 28, 2017
Provide housing for 298 flood victims in India
By J Ranga Rao | Project Leader
![Masonry work is being done.]()
Masonry work is being done.
This project "To Provide Housing for 298 Flood Victims in India" has been successfully implementing in the Avanigadda and Nagayalanka Mandals of Krishna District in Andhra Pradesh, India. Since the villagers of these two mandals are severely affected during the floods, ASSIST staff are motivating to the flood victims and bringing them into normal life. ASSIST has taken the initiative to build new houses for the flood victims and construction of new houses to these flood victims is underway with the support of generous donors through GlobalGiving.
The following information shows the status of the Construction of 298 Houses to the Flood Victims in Avanigadda and Nagayalanka Mandals in India.
- Houses fully completed with sanitary latrine– 17
- Houses completed but not the latrine – 17
- Houses completed but flooring yet to be done– 50
- Houses with roof slab completed – 57
- Houses come up to roof level – 11
- Houses come up to lintel level – 8
- Houses come up to window sill level – 9
- Houses come up to Basement level – 15
- Houses not started yet -113
We look forward to the continued support from the generous donors in order to complete the rest of the houses.
Thank you for you kind support as your support gives the new hope to the flood victims.
![Construction work is in progress.]()
Construction work is in progress.
![Walls are being constructed.]()
Walls are being constructed.
![Door are being erected.]()
Door are being erected.
Dec 2, 2016
Providing housing for 298 flood victims in India
By J Ranga Rao | Project Leader
![House is being constructed]()
House is being constructed
This project "To Provide Housing for 298 Flood Victims in India" has been successfully implementing in the Avanigadda and Nagayalanka Mandals of Krishna District in Andhra Pradesh, India. Since the villagers of these two mandals are severely affected during the floods, ASSIST staff are motivating to the flood victims and bringing them into normal life. ASSIST has taken the initiative to build new houses for the flood victims and construction of new houses to these flood victims is underway with the support of generous donors through GlobalGiving.
The following information shows the status of the Construction of 298 Houses to the Flood Victims in Avanigadda and Nagayalanka Mandals in India.
- Houses fully completed with sanitary latrine – 17
- Houses completed but not the latrine – 17
- Houses completed but flooring yet to be done – 52
- Houses with roof slab completed – 57
- Houses come up to roof level – 12
- Houses come up to lintel level – 8
- Houses come up to window sill level – 9
- Houses come up to Basement level – 15
- Houses not started yet -115
We look forward to the continued support from the generous donors in order to complete the rest of the houses.
Thank you for you kind support as your support gives the new hope to the flood victims.
![House is ready to get slab]()
House is ready to get slab
![House construction is being done]()
House construction is being done
![House is being constructed]()
House is being constructed