Again, here is another brief report of the Help Takijah build a Nursery school. It has been a wonderful time seeing the work in progress. We are looking forward to completing the cementing of the verandas to have the the structure protected from erosion come the rainy season in March.
The Children have continued to have the anxiety to see the completed cemented from within and without painted. It is hour hope that once we are through with the cemennting the verandas round, and putting the ceilings, we willthen move to painting.
I really very much want to thank the supporters of this project and to iinform that only alittle push is left for us to complete and put the nursery school up the taste of the time.
We look forwards for a final push for all everyone so that we can complete the project before June 2015.
Pictures willbe available in our next report showiing the veranders cemented and other works.
Remain blessed.
Dear all,
The project is going on very well. We have completed the plastering of the outside, cemented the floors and fitted the windows.
The pictures attached tre the plastering/cementing works.We are now left with the painting of the ceiling.
We thank all the supporters of this project. Schools have re-opened and the pupils will be happy getting into thier classrooms which are well plastered and cemented.
All the above work took place during the long vacation. We will be left with completing the cementing and plastering of all the other classes. Afterwhich painting will take place before the kids can fully enjoy thier classrooms.
We are still appealing to all the supporters of this project to continue with thier work as God loves a cheerfull giver.
Yours faithfully.
It is another time for the report again. After our last report, work continued in the school . I am glad to report that the doors and windows have been fitted and what is left now is the cementing of the floors and plasltering the side and back parts of the building.
We decided to put the doors and window shutters because to avoid stray animals from entering the well plastered class rooms and office. I am glad to report that work is going on sucessfully.
This is summer holidays and we are expecting volunteers from to arrive on the 15th of July so that we can get on with the flooring and plastering of the back and side parts.
At the time of writing this report since were are already cut up by time the pictures are still being awaited. As soon as the pictures arrive I aill add a new report because work is going on at the time of reportiing.
I want to believe that by Septmber, the school shall be painted and put to use even before putting the ecelling boards.
May God continue to bless the charital hands of this project.
Respecfully submitted by,
Wirkom Fred ,,
Project leader
Dear everyone,
It is another time again for me to give you a progress report on this project. As you can see from the previous report, the structure was not yet plastered. After the report, we had concentratred on the plastering of the internal and external walls of the project. We have done much as you can take a look on the pictures attached.
We also completed the gables and and dug the surrounding to make sure that with the work that has been done, the rain water whould not get into classes.
After the last disbursment, we acquired more cement which has been used for doing the plastering as you can see in the pictures attacahed.
I am glad to inform every one that that the Head teacher of the Primary section assigned senior primary pupils to help carry water for the plastering each time we needed water. The teachers and parents together with the primary school pupils really gave us a wonderful supporot in terms of local labour and water supply since the school has got water.
The Headmistress's office has been properly plastered and well leveled while the wall Black Board is to be completed and possibly presented in the next report and possibly with the floors already cemented depending on our financial means.
The project has really gone a long way and I have the honour to thank all the donors who had supported this project especially within this quarter which we are waiting for the disbursement. I pray that as this reports are giving you the updates on where your money is going and what it is used for, may you call on your friends, relatives and even colleagues to join your course for the project to be compleded and put to us as soon as possible.
The Pictures attached are only few of the activity pictures. There are some where children are transfering bricks which was packed in one of the rooms for the gables, some carrying water and some with parents helping to dig the surroundings.
The progress of the project is being experience and appreciated by every one in the village.
May God bless you all as you read through this progress report.
Happy Christmas and New Year in Advance. The Takija Nursery school is waxing strong and the construction project is in progress in accordance with the available financial resources.
We hope that before the year runs to an end we would have gone far with with the project. What is left now is the flooring and the fittings.
We have been builing the capacity of the the teachers and and our volunteers have been visiting the school, taking part in teaching and playing games with them.
At the mooment they are on a christmas holiday to resum on the 6th of the January. They all did well in the first term examination.
I have the honour to thank all the supporters of this project and those who would still like to support it so that we can complet the project to enable them study in a conducive environment.
Links:
Project Reports on GlobalGiving are posted directly to globalgiving.org by Project Leaders as they are completed, generally every 3-4 months. To protect the integrity of these documents, GlobalGiving does not alter them; therefore you may find some language or formatting issues.
If you donate to this project or have donated to this project, you will get an e-mail when this project posts a report. You can also subscribe for reports via e-mail without donating.
We'll only email you new reports and updates about this project.
Support this important cause by creating a personalized fundraising page.
Start a Fundraiser