Clean Water & Sanitation for Kenyan Primary School

by Kenya Rainwater Association
Clean Water & Sanitation for Kenyan Primary School
Clean Water & Sanitation for Kenyan Primary School
Clean Water & Sanitation for Kenyan Primary School
Clean Water & Sanitation for Kenyan Primary School
Clean Water & Sanitation for Kenyan Primary School
Clean Water & Sanitation for Kenyan Primary School
Clean Water & Sanitation for Kenyan Primary School
Clean Water & Sanitation for Kenyan Primary School
Clean Water & Sanitation for Kenyan Primary School
Clean Water & Sanitation for Kenyan Primary School
Clean Water & Sanitation for Kenyan Primary School
Clean Water & Sanitation for Kenyan Primary School
Clean Water & Sanitation for Kenyan Primary School
Clean Water & Sanitation for Kenyan Primary School
Clean Water & Sanitation for Kenyan Primary School
Clean Water & Sanitation for Kenyan Primary School
Clean Water & Sanitation for Kenyan Primary School
Clean Water & Sanitation for Kenyan Primary School
Clean Water & Sanitation for Kenyan Primary School
Clean Water & Sanitation for Kenyan Primary School

Project Report | Jul 5, 2016
Progress Report -Murichu Pri School WASH Project

By Florence Chepkoech | Project Leader

Happy New Month July 2016!

I am pleased to share with you our developments for the past three months at Murichu Primary School, Kenya WASH Project, I had said I will keep you posted. Happy reading!

Background

The following are the project components: (a) construction of 75m3 masonry rainwater storage tank; (b) installation of gutters including a foul-flush system; (c)Construction of draw-off point for pupils; (d) construction of gender-segregated VIP latrines (blocks for girls, boys, and teachers); and (e) training of pupils and community on good hygiene practices.

Project Implementation Status

Procurement of Construction Material

The procurement process for the supply of construction material was done through competitive bidding. The selected supplier has already supplied all the construction material for the tank as per the BoQ/LPO and paid as per signed deliver notes and invoice. The quality of the material was ascertained before the payment was done. The material is on site and well secured after delivered.

Construction of the 75m3 water storage tank

The construction process has so far achieved the following activities:

a) Site identification, clearance and set-up

The siting of the tank location was done during the project launching meeting on May14, 2016.

Site clearance involved the removal of vegetative from the identified site.

Setting out the tank entailed identification of a reference point that marked the center of the tank. Then a radius 3.4 m in reference to the tank center was used to determine the internal and external circumference of the tank.

b) Tank foundation

Excavation of the foundation strip, which went up to 1.5m due to the deep of unsuitable clay soil. The five reinforcement concrete (1:2:3 mix ratio) columns’ footings of 0.6x0.6x0.6m were dug up to 2.1m – up to the stable murram layer.

The foundation walls were constructed with three courses of 9x9x9-inches quarry stones using mortar joint ratio mix of 1:3 including along the two diameters cross-sections – from the four side reinforced columns.

The tank foundation was filled with hardcore (rubble stones), which was compacted up to the level of the walls. The spacing between the wall and the excavated pit was also filled with compacted hardcore.

The Y12 reinforcement net was placed at 150mm spacing and well secured with bidding wire, and then the concrete slab (1:2:3 mix ratio) was casted.

The tank capacity will be increased by an extra depth of 0.75m due to the deep tank foundation – this will be more cost-effective instead of filling the extra depth with hardcore.

 

AI would like to thank you for your generous contributions, Murichu Primary will soon have enough WASH facilities, and handwashing will drastically reduce cases of diarrhoea. Absenteeism will go down too as water will now be available within the school. Clean water and sanitation has the potential to make a difference in children’s lives. Kids need clean water to be healthy, to grow and thrive, to attend school regularly, and to fulfil their potential.

Thank you so much for your continued support and collaboration, together we can! Enjoy reading and have a fruitful month ahead!


Attachments: Share on Twitter Share on Facebook

About Project Reports

Project reports on GlobalGiving are posted directly to globalgiving.org by Project Leaders as they are completed, generally every 3-4 months. To protect the integrity of these documents, GlobalGiving does not alter them; therefore you may find some language or formatting issues.

If you donate to this project or have donated to this project, you can receive an email when this project posts a report. You can also subscribe for reports without donating.

Sign up for updates

Organization Information

Kenya Rainwater Association

Location: Nairobi - Kenya
Website:
Kenya Rainwater Association
Peris Muchina
Project Leader:
Peris Muchina
Information and Communication Officer
Nairobi , Nairobi Kenya

Retired Project!

This project is no longer accepting donations.
 

Still want to help?

Find another project in Kenya or in Clean Water that needs your help.
Find a Project

Learn more about GlobalGiving

Teenage Science Students
Vetting +
Due Diligence

Snorkeler
Our
Impact

Woman Holding a Gift Card
Give
Gift Cards

Young Girl with a Bicycle
GlobalGiving
Guarantee

Get incredible stories, promotions, and matching offers in your inbox

WARNING: Javascript is currently disabled or is not available in your browser. GlobalGiving makes extensive use of Javascript and will not function properly with Javascript disabled. Please enable Javascript and refresh this page.