By Adam Rouhana | CEO
PROGRESS TIMELINE
Demolition | April 2019
Demolition of the old, earthquake-damaged building is complete. Measurements were taken in coordination with the Nepal Civil Works and Engineering Office.
Foundations Dug | May 2019
Foundation work for the first three classrooms was completed in May and materials were procured and delivered to the site. Steel rebar classroom frames were erected.
Concrete Poured | May 2019
Brick was laid at the end of May and concrete has been poured. Construction of the first three classrooms will be complete by July.
Hexagonal Classroom | June 2019
Construction of Diyalo's hexagonal classroom has also begun. The foundation is being dug and rod fabrication is ongoing. Estimated completion date is the end of June.
Toilet Construction | July 2019
Construction of the toilets will begin by the last week of June. The toilets will take 2-3 weeks to build. All school construction will be complete by end of July.
We want to extend a special thank you to GlobalGiving Grants for making this project possible through a $10,000 construction grant. Thank you.
For the full report click here - https://mailchi.mp/779b9ae4e180/sewalung-update
Links:
By Diyalo Foundation | Staff
By Diyalo Foundation | Staff
Project reports on GlobalGiving are posted directly to globalgiving.org by Project Leaders as they are completed, generally every 3-4 months. To protect the integrity of these documents, GlobalGiving does not alter them; therefore you may find some language or formatting issues.
If you donate to this project or have donated to this project, you can receive an email when this project posts a report. You can also subscribe for reports without donating.