Tabulated table of progress of activities against outputs, outcomes and comments for disparities in performance.
Planned activities
Outputs
Outcomes/Achievements
Remarks
Construct 13 panel toilets
Constructed 6 panel toilets
Increased access to sanitation facilities
Work still on -going
Construct 5 ECOSAN toilets
No ECOSAN toilets constructed
Two toilets already roofed, work at
Work on going
Construct 40 sanitation platforms
No sanitation platforms provide yet to support household latrine construction
None
Moved to third quarter to allow sinking of pits
Protected and rehabilitate 3 springs
No springs protected and rehabilitate springs yet
None
Identification of sites on going
2 boreholes rehabilitates
5 boreholes rehabilitated.
Functionality of water sources increased from 70% to 95%
Done by trained community mechanics.
Drill 8 rain water tanks
8new boreholes rehabilitated.
Access to safe water increased from 42% to 56% due to construction of new sources.
All done.
Install 5 rain water tanks
Five 10,000 litre rain water tanks installed.
Increased access to safe water in primary schools.
All tanks delivered and installed.
Construct 8 household water jars
No household water jars constructed yet
None
Procurement of mould on going
Construct 4 shallow wells
No shallow wells constructed yet
None
Work on going
26 sanitation kits provided to schools
Provided schools with 27 sanitation kits.
27 pit latrines have been sunk and construction going on, due to provision of sanitation kits to schools.
Kits distributed in all the schools.
240 sanitation kits given to 6 parishes
Provided 213 sanitation kits to 6 parishes
33 pit latrines have been dug at house hold community level due to distribution of kits at
All provided.
Parishes.
3 sub – county health committee
Facilitated 3 sub county committee meetings.
Sub – county plans have been reviewed in these meetings. By –laws on water and sanitation have been proposed.
All conducted
6 parish sanitation committees established
Established and trained 6 parishes sanitation committees
Improved data collection and sanitation
All established and trained.
12 water source committees established
Established and trained 12 water source committees
Contributed to the increased functionality of water sources.
All established and trained with in the quarter.
3 hand pump mechanics trained
Established and trained 3 hand pump mechanics
All repairs on water sources done and completed by the trained hand pump mechanics
3 mechanics trained on O & M of water sources.
21 water quality surveillance testing done
21 water quality and water borne diseases surveillance done
Hygiene and environmental improvement messages have been targeted based on the water quality reports.
Surveillance done in the four parishes of Ojom, Owelai, Katine and Merok.
Networking with partners
Plan for and participate in national sanitation week
Planed and participated in National sanitation week activities.
Improved household sanitation
Attend district WES co-ordination meeting
Attend 1 District WES coordination meetings
Integrated the project water and sanitation plans into the district water source plans
Attend and made presentation
1
Attend 1 best practice sharing meeting on safe water provision - AFRICARE
Integrated the project water and sanitation plans into the district water sector plans
Attend
Planned activities
Outputs
Outcomes/Achievements
Comments
Community information sessions with IEC materials on the community’s rights to basic services such as water, health, education.
One meeting was held
Consensus from the sub-county technical officials and key partners (NGOs) was reached on the need to reproduce existing IEC materials for all components.
Meting successfully held with 100% turn up.
2 workshops with key district partners to review and identity required IEC
2 workshops held
Major/priority issues of focus and key IEC messages developed for the reproduction of the IEC materials
As above
6 Village level Focus Group Discussions (FGD) to pre-test the applicability of IEC materials
6 FGD held
FGDs guides developed
This activity was not conducted because of the delay in holding district stakeholders update meeting but re-planned in the next reporting period.
1 feedback meeting with key district partners on the IEC materials developed
1 feedback held
IEC messages shared and consensus reached IEC to be pre-tested and reproduced
One on one meetings were organized instead of formal meetings.