Breakdown and estimated cost for Drydocking and Reconstruction
1
Required Steel Plate: - Ship's Hull, bottom plates, stiffener, profile, etc. 50 Tons x Tk 1,20,000 (approx.) - Cost of material & workmanship of the hull, superstructure, and underwater hull portion.
8,300,000.00
Quantity of plate for underwater portion can only be determined upon docking of ship.
2
Accommodation & Medical area of ship:- Paneling, floor epoxy works, interior furniture, sanitary system repair, New installation of water purifier for safe drinking and cooking water, new installation of split type air conditioner, Thai glass door & windows, and overall painting, material & workmanship.
4,502,000.00
All types of material are required upon the volume of reconsutruction.
3
Outfitting works:- Piping, Railing, Hatch, Bollard, Stairs, miscellaneous steel repair works, anchor & chain cleaning, repair or renewal, and painting including installing water purification system material & workmanship.
3,550,000.00
Cost may vary upon volume
4
Cost of Paint & painting works:- Ship's hulls, bottom including underwater area & the designated Logo artwork.
2,200,000.00
Epoxy based paint for underwater portion.
5
Slipway and Docking charges:- Ship & Houseboat docking and undocking including Slipway charges, trolley shifting, sand blasting, electric supply, toilet facility, garbage disposal, security services, UT Gauging, use of cranes / forklifts & all other related works (90 days approx.)
2,800,000.00
Duration of slipway time is dependent upon extent and scope of works recommended by GoB Surveyor and fair-weather condition.
6
Cost of towing Ship, and Houseboat From the dockyard to designated service location by hired Tugboat.
1,500,000.00
The estimated cost will be determined by the procurement & supply Dept.
7
Infrastructural, and logistic costs: Temporary shed erection cost at Gaibandha for shore-based medical services including material & labor costs, accommodation for medical staff at Gaibandha Fleet staff at Narayangonj, and storage space for medical equipment, and furniture, including food.
1,000,000.00
Budget is estimated & based on previous experience. This includes salary staff and other related costs as stated.
8
Additional costs: - Safety and security of the ship, full-time supervision, monitoring, and quality assurance, by Fleet Head Office staff, Survey by GoB DG Surveyor, approval of the ship’s design, new registration of the ship, and management & contingency cost.
3,400,000.00
Dismantling, shifting, and carrying medical equipment & furniture including non-essential ship items & equipment for safe-keeping in storage and return & installation on the new ship
Total Amount:
27,252,000.00
VAT (10%) on Dockyard works:
2,725,200.00
GRAND TOTAL: