By Karolien Remmerie | Director
The construction of the Assistive Device Innovation and Training Center in Kamangu, Kiambu County, is a key initiative by the Special Education Professionals (SEP), through your support, to improve the lives of children with disabilities and their families across Kenya. The center will serve as a hub for the production of affordable customized assistive devices and caregiver training.
The contractor’s monthly progress reports indicate that the project has remained on schedule with no major implementation constraints reported. Site activities have continued smoothly, supported by proper coordination, availability of materials, and adherence to construction timelines and quality standards. Recent site photographs further demonstrate the steady advancement of the construction works and the commitment toward timely completion of the facility.
Major milestones achieved during this period are included on the table below:
Work Progress Breakdown - Central Building
Implementation Break down Status
1. Contract signing and site handover Activity Completed
2. Site mobilizition Activity Completed
3. Site clearance Activity Completed
4. Setting out and excavation Activity Completed
5. Blinding for strip footing Activity Completed
6. Form working and concreting of strip foundation Activity Completed
7. Substructure walling Activity Completed
8. Backfilling works with murram, hardcore, quarry dust and DPM Activity Completed
9. Reinforcement, form working and concreting of slab in foundation Activity Completed
10. Super structural masonry walling Activity Completed
11. Form works and columns Activity Completed
12. Ground floor and roof slab Activity Completed
13. First floor walling Activity Completed
14. Roofing slab Activity in Progress
15. Parapet walling Activity to proceed as scheduled
16. Opening doors and windows Activity to proceed as scheduled
17. Finishes, external and Internal walls, floor, ceiling finishes,
electrical, mechanical and painting works Activity to proceed as scheduled
Once completed, the Assistive Device Innovation and Training Center will significantly enhance access to locally made assistive devices and specialized training, contributing to a more inclusive society where children with disabilities can fully participate and thrive.
Project reports on GlobalGiving are posted directly to globalgiving.org by Project Leaders as they are completed, generally every 3-4 months. To protect the integrity of these documents, GlobalGiving does not alter them; therefore you may find some language or formatting issues.
If you donate to this project or have donated to this project, you can receive an email when this project posts a report. You can also subscribe for reports without donating.
Support this important cause by creating a personalized fundraising page.
Start a Fundraiser