By Karlheinz Neumann | Founder and Project Leader
In July 2021 we started renovating the 4300 sqft. “U-Block”. It will be the largest single construction project in the entire ten-building school complex. We expect total costs of approx. USD 42,000 for building renovation, roof, doors and windows, plastering, painting and tiling the floors.
What has been achieved so far?
The masonry work required for the basic renovation of the building has now been almost completely done, such as
What about the costs?
We will have some additional costs of around USD 3,200 for various good reasons for the masonry work:
What’s coming up soon?
The new roof is then erected on the relevant parts of the building; windows and doors are produced in parallel. The walls are then plastered. If all goes well, the work should be completed in the 1st or 2nd quarter of 2022.
The completion of this school building will be a significant relief for the high number of students as we can provide several additional classrooms. Today, due to lack of space, up to 300 students from several classes are taught in one classroom.
Thank you so much for your support.You can make it happen.
Please watch a 10 minute video what we accomplished so far. See LINK below.
Links:
By Karlheinz Neumann | Founder and Project Leader
By Karlheinz Neumann | Founder of HUMAN Stiftung and Project Leader
Project reports on GlobalGiving are posted directly to globalgiving.org by Project Leaders as they are completed, generally every 3-4 months. To protect the integrity of these documents, GlobalGiving does not alter them; therefore you may find some language or formatting issues.
If you donate to this project or have donated to this project, you can receive an email when this project posts a report. You can also subscribe for reports without donating.
Support this important cause by creating a personalized fundraising page.
Start a Fundraiser