Thank you for standing by us and supporting the construction of this school where 176 students eagerly await to start studying in purpose build classrooms!
The Zarbaig School is going to be a double story building. Right now the ground floor is under construction. The school building once completed will have:
I visited to the DIL School Zarbaig on 10th Dec-2014. Almost 50% of the construction is complete. Construction work is proceeding smoothly as per plan and our estimated time for completion of this task is March, 2015.
Meanwhile students continue to attend school in the old one room building. There are 118 girls and 58 boys enrolled in the school. The school closed for winter vacations on 12th December. As this is a winter zone school, the winter holidays are longer and schools will reopen in late February. With the recent tragedy in the Peshawar school, where nearly 150 students were killed, it has become even more important to provide our girls, and boys, a safe and secure school where they can complete their education. The students, parents and teachers of Zarbaig school are determined not to be cowered by anyone and eagerly await their school to open.
Project reports on GlobalGiving are posted directly to globalgiving.org by Project Leaders as they are completed, generally every 3-4 months. To protect the integrity of these documents, GlobalGiving does not alter them; therefore you may find some language or formatting issues.
If you donate to this project or have donated to this project, you can receive an email when this project posts a report. You can also subscribe for reports without donating.