LOVING HOME AND EDUCATION FOR ORPHANS IN UGANDA
By Jagoda Kalisz | Project Leader
![LAND IN MASAKE UGANDA, WHERE WE WILL BUILD]()
LAND IN MASAKE UGANDA, WHERE WE WILL BUILD
- After publishing the collection on GlobalGiving, Equator University of Sience and Technology, Masaka Uganda came forward and offered us land for free to build an orphanage. within a few weeks the land will be transferred to our Foundation Name. We where there already, we saw the land, its beautiful. We attach a photo of the ground in the attachments.
- ORPHANAGE CONSTRUCTION TIMELINE
- NOW - 06.24 obtainingamestimatedconstructionvaluation from a potentialcontractor/ preferablytwodifferentones/
- 04.24-08.24
- determining the exactlocation, shape and size of the plot
- geotechnicalresearch for the plot to determinatepossiblefoundation and underground waterlevel
- checkingavailability for utilitysupplies (water, electricpower, teleinformatics, sewageutilisation)
- preliminaryestimatedtable of quantities for construction
- obtainingmapsshowing the topography of the plot and location of greenary
- 08.24 - 10.24
- necessarychanges to the conceptual design to adapt to a given plot
- addingconceptual MEP design
- 10.24 - 02.25
- finding and employing a localcoordinator of administrativeprocesses
- finding and employinglocaldesigners (construction & MEP) to adapt the project to applicableregulations
- searching for companies and organizationsthatmay be interested in donating materials orfounding for construction as part of the promotion (organizationspromotingbamboo, governmentorganizationspromotingecology)
- 02.25 - 08.25
- preparing the project for localregulations and obtainingallnecessaryadministrativepermits
- 08.25 - 11.25
- selection of the facilitycontractor, signing of contracts
- preparation of the site for construction - cleaningworks, necessaryfelling, marking out the constructionsite
- establishing a detailedconstructionschedule and the constructionfinancing dependent on it
- 11.25 – 10..26
- Mainconstructionphase - construction of the mainbuilding, bedrooms and sanitarybuildings for children, 2 guestbuildings, auditorium
- 10.26 - 04.27
- MEP works, constructionfinishing, indoor and outdoorfurniture and landscapingworks
- Tidyingup the constructionsite and moving the children to theirnewhome
Employing orphanage caregivers and conductingtraining in cooperation with operatingorphanages in Entebbe
- We have finished recording a professional movie about our activities, with which we want to appear on popular television in Poland. We expect this to be our turning point. We attach a link to the video on Youtube
https://youtu.be/UJdJT8ukkLo
- We still support 120 kids in Ruihja, also we rented house in Entebbe where we have now 6 orphans. Til the end of the year we will have 12 kids. You can see the house in the movie we attached.
-
![NEWEST TWO ORPHANS WE ADOPTED LAST WEEK]()
NEWEST TWO ORPHANS WE ADOPTED LAST WEEK
![CHILD CARE IN ENTEBBE SLUMS]()
CHILD CARE IN ENTEBBE SLUMS
![WE BOUGHT GOATS FOR CHILDREN IN RUHIJA]()
WE BOUGHT GOATS FOR CHILDREN IN RUHIJA
Links:
Attachments: