By Kwasi Twumasi | President
Second Quarter Report
- We are making great progress in the year 2014. At the beginning of the year we embarked on the first phase of electrical wiring of the orphanage facility building. Conduits and wires were laid throughout the building to all places where electrical gadgets will be installed.
- Following the completion of the electrical wiring, the first phase of plumbing works was initiated. PVC pipes were laid to the kitchen, bathrooms, and all places where final plumbing gadgets will be installed.
- Ceiling works began immediately after the plumbing tasks were completed. The entire building (both inside & outside) have been sealed with plywood. This helps to avoid insects like mosquitoes coming into the building. It also protects the roof from being blown away by strong winds.
- The next major task that has just begun is the plastering of the entire building with mixture of sand and cement. Also the entire floor will be cast. This work is in progress now and is expected to be completed by the end of August 2014.
- When plastering is done by the end of August of this year, the next major tasks that are planned to be completed before the end of the year are:
We thank you for your continual support. We could not have made this much progress without your help. We pledge to use all donations to our organization exclusively for the work. None of the leaders in the organization is paid. Our work is purely voluntary, just to help take care of poor African orphans.
Any financial support is welcome. Nothing is too small. Thank you.