Estudio Damgo III: A Filipino Design+Build Studio

by Foundation University
Play Video
Estudio Damgo III: A Filipino Design+Build Studio
Estudio Damgo III: A Filipino Design+Build Studio
Estudio Damgo III: A Filipino Design+Build Studio
Estudio Damgo III: A Filipino Design+Build Studio
Estudio Damgo III: A Filipino Design+Build Studio
Estudio Damgo III: A Filipino Design+Build Studio
Estudio Damgo III: A Filipino Design+Build Studio
Estudio Damgo III: A Filipino Design+Build Studio
Estudio Damgo III: A Filipino Design+Build Studio
Estudio Damgo III: A Filipino Design+Build Studio
Estudio Damgo III: A Filipino Design+Build Studio
Estudio Damgo III: A Filipino Design+Build Studio
Estudio Damgo III: A Filipino Design+Build Studio
Estudio Damgo III: A Filipino Design+Build Studio
Estudio Damgo III: A Filipino Design+Build Studio
Estudio Damgo III: A Filipino Design+Build Studio
Estudio Damgo III: A Filipino Design+Build Studio
Estudio Damgo III: A Filipino Design+Build Studio
Estudio Damgo III: A Filipino Design+Build Studio
Estudio Damgo III: A Filipino Design+Build Studio
Estudio Damgo III: A Filipino Design+Build Studio

Project Report | Jun 18, 2015
Floating Pyramid on Brgy. Bantayan Sea

By Florabelle T. Caloy | Student Leader

Diver putting a marker
Diver putting a marker

Seeing the Marine Sanctuary Center floating on the sea is a dream come true to the design team of Estudio Damgo III for nine months ago (August 2014) all we have was just the miniature model we tested on the same site.

March 2015 was supposedly the deadline of the project but due to some circumstances that is out of the team’s control, the construction was extended for another two months. But despite this, we never ceased to continue the dream we have from the very beginning. We took a break on April and came back on the month of May. We reorganized, made some adjustments on the schedule and the work distribution in order to bring back the momentum we have before the break. Laying out the markers on the actual site (which is approximately 200 meters away from the boulevard), dropping the deadman (concrete foundation), Lifting and floating the base structure, and assembling the upper structure were the major activities for the last few weeks of construction.

The divers from Dauin volunteered themselves to help the team with things that needs to be done underwater. Fully geared, the four divers laid out the nine buoys as markers of the building on the second week of May. The following week, the entity that poured the concrete on the formworks of the concrete foundation delivered it to the site. But we were not able to bring the foundation on its actual location that day. Lifting it was impossible with the plan we initially have. It was a nightmare! The people who helped lifting have used all their energies but it didn’t make any difference. Given that situation, the team thought of a plan B to drop the foundation in place. They fabricated a steel raft with barrels as the floatation to be the courier of the concrete foundation from the shoreline to the site. The A-frame and a chain block at the shop were the solution to the challenge encountered in lifting the deadman. And thankfully, we were successful on our second attempt! The lead diver, was the one who gave the command and direction to those who volunteered in pulling and dropping the concrete on site. The Philippine Coast Guard were also there to help the team, they sent their men equipped with aluminum boat and diving apparatuses.

The spirit of camaraderie and unity was the key to the accomplishment of lifting the platform of the structure to the sea. People from Barangay Bantayan, Foundation University workers and Estudio Damgo III team lifted the base structure with our bare hands. Slowly, we slide the structure into the ramp down to the sea and in a span of five hours, we are able to float the two 4m X 8m base structure modules on the water. That time, the team showed that “bayanihan” still exist these days.

Estudio Damgo III team with the workers then started to construct and assemble the upper portion of the structure. It wasn’t easy assembling it on top of a moving water especially when the weather is bad or when the wind is blowing hard. But these factors didn’t stop us in completing the project. The upper structure is almost done both its exterior and interior. The project will be inaugurated on July 2, 2015.

Lifting the Concrete Foundation
Lifting the Concrete Foundation
Transferring the base structure
Transferring the base structure
Louvers partially installed
Louvers partially installed
building interior
building interior
Building exterior almost complete
Building exterior almost complete
Share on Twitter Share on Facebook

About Project Reports

Project reports on GlobalGiving are posted directly to globalgiving.org by Project Leaders as they are completed, generally every 3-4 months. To protect the integrity of these documents, GlobalGiving does not alter them; therefore you may find some language or formatting issues.

If you donate to this project or have donated to this project, you can receive an email when this project posts a report. You can also subscribe for reports without donating.

Sign up for updates

Organization Information

Foundation University

Location: Dumaguete, Negros Oriental - Philippines
Website:
Facebook: Facebook Page
Project Leader:
Anna Marie Cale
Dumaguete , Negros Oriental Philippines

Funded Project!

Combined with other sources of funding, this project raised enough money to fund the outlined activities and is no longer accepting donations.
   

Still want to help?

Support another project run by Foundation University that needs your help, such as:

Find a Project

Learn more about GlobalGiving

Teenage Science Students
Vetting +
Due Diligence

Snorkeler
Our
Impact

Woman Holding a Gift Card
Give
Gift Cards

Young Girl with a Bicycle
GlobalGiving
Guarantee

Get incredible stories, promotions, and matching offers in your inbox

WARNING: Javascript is currently disabled or is not available in your browser. GlobalGiving makes extensive use of Javascript and will not function properly with Javascript disabled. Please enable Javascript and refresh this page.