By Maiko Okamoto | Vice Leader
We had a lot of snow at the New Years’ holiday, and also we were short of construction material. So now the schedule is late. However, builders and qualified architect of the first class managed to adjust andalter the progress of the work. And made it possible that we finished the arrangement of reinforcement and formwork. In March we started a building of steel flame construction.
After this, we start roofing service, deck concrete placing, installing metal-framed glass sliding doors, and wall.
The constructor said that because of the lack of funds or construction vehicle shortage, it was very hard to work out a plan. However, we try to respond current condition flexibly to make construction smooth.
Future schedules
April 2014: roofing, wall, and installing glass sliding doors
May 2014: interior finishing, sanitary facilities, electrical equipment, and kitchen equipment
June 2014: interior finishing, fire protection facility, furniture work, and inspection by fire authorities and health canter
July 2014: opening