By Isabel Cristina Ospina Cano | Isabel Cristina Ospina Cano
On September 19, 2022, construction work began on the new headquarters of the Corporación Hogar: A place to fulfill dreams. A building that will consist of 5 floors and will offer social programs to 500 boys, girls and young people from the city of Medellín and Antioquia. Today
Technically Until today, the 18 required piles have been excavated and emptied, and the total excavation of the basement has been done, which totaled 315 m3. The excavation of the sub-route of the elevator (-1.40 m) and the demolition of the false rings and rocks of the basement to free the space for the columns and beams has also been done. The dice, screen and beams, dice and slab of the elevator pit and columns have been emptied. All the elements have been covered with fique to facilitate its hydration.
We continue with the Management of the project, donated by the prestigious company from Medellín, Londoño Gómez, with 50 years of experience in the city of Medellín and the country. The supervision by the company ICP S.A.S and the construction company INVECTOR S.A.S of the city of Cali.
We continue with the management of resources because we are still raising money to bring the construction to a successful conclusion. Natural persons, companies or organizations can be linked as follows:
1. Cash donations through the GlobalGiving platform
2. Discounts on materials
3. Donation of materials
We need yor help
Project reports on GlobalGiving are posted directly to globalgiving.org by Project Leaders as they are completed, generally every 3-4 months. To protect the integrity of these documents, GlobalGiving does not alter them; therefore you may find some language or formatting issues.
If you donate to this project or have donated to this project, you can receive an email when this project posts a report. You can also subscribe for reports without donating.
Support this important cause by creating a personalized fundraising page.
Start a Fundraiser