By MARIA CORAZON S. BERNARDEZ | PROJECT LEADER
FEBRUARY 22, 2020
The bamboo structural details were completed and the "saksak" roofing was completely installed.
FEBRUARY 25, 2020
The group members started skinning the "botong" bamboo that will be used for the ground floor flooring while some started installing the plywood for the mezannine floor.
MARCH 2, 2020
The group members started installing bamboo slats dor the window.
MARCH 7, 2020
The bamboo flooring was completely installed in the ground floor area.
MARCH 12, 2020
The terracotta clay tiles were installed on the front and side steps of the entry to the house.
MARCH 14, 2020
Window slats and door jambs were completed and ready for installation.