Dear donors, we would like to give you an update of the construction of the Civic Center in Pieve Torina.
February 2021 - completed the steel supporting structure and the laying of the wooden roof, the the company continues with the casting of the intermediate floors and begins the external cladding of the building
March 2021 - the company continued with the realization of the external infill and with the coating fire protection of the load-bearing structure and start laying the outer coat.
April 2021 - The company continued with the construction of the outer coats, the laying of the insulators begins in rock wool inside the walls, the creation of the internal partition walls in plasterboard and plant arrangements. Then it proceeded with the casting of the first lightened screed to cover the systems and the closing of the plasterboard walls inside the gym began.
May 2021 – The building company carried out the installation of the radiant floor system and continues to close the internal plasterboard cladding.
We are grateful for all you support up to now. We need further funds to complete this building that will benefit the whole community of Pieve Torina