Aug 11, 2023
Empowering Culebra Project
The process linked to the authorization of the installation of the solar systems –with storage infrastructures– in 24 essentials businesses in Culebra Island, has continued. This has...
Apr 5, 2023
Empowering Culebra
Working on a project of this magnitude and with mostly federal requisites to fulfill has taken more time than projected. However, it has been such a satisfactory journey until now that we have the...
Dec 6, 2022
A Community solar project in the making... Empowering Culebra
Five years have gone by since Hurricanes Irma and María struck our archipelago. After that, we’ve undergone earthquakes and COVID-19 pandemic in 2020 and Hurricane Fiona in 2022. These...