Water Report March 2015

Manjanda using a plastic bottle as filter
Manjanda using a plastic bottle as filter
Following on from Alan Stitchcombes visit in March 2014 it had been decided to ask a specialist from Abong Mbang to visit  and provide estimates of feasibility and costs for improving the two springs and the possibility of digging a well. Sadly the man in question Mr Aberdjine died in July before he could visit the site so when we arrived in January 2015 we were no further forward.
On arrival we found that the first spring {nearest Gbine} had been rendered useless by a rise in water level due to damming of the stream and pollution from the alcohol stills on the bank. However the second spring {Mokolobar’s} was still flowing and being used by both the Baka and the village, despite the mud, leaf litter and frogs that abound.
We contacted Samuel Owoundi, a local entrepreneur, who sent us his sub-contractor, Moise Akombombo who had experience in spring capture. Having given us an estimate of 300,000 cfa and explained his proposed method it was decided to proceed at once, while we were on site to help and supervise.
A meeting with the village elders assured us of their support so we started work the next day. A large tree that had fallen just in front of the spring had to be cut through to improve access. The wood was used to provide shuttering boards for the work and to rebuild the bridge over the marsh.
A new path was cleared and widened to allow easier transport of sand and cement, then the waiting began. First it was delivery of materials that were delayed, then Moise’s father suffered an accident which meant that he needed regular visiting, so work only advanced sporadically. However with the help of the Baka workers and Andi’s hard work it was completed on time. 
The water level was successfully raised by about 30cm and by digging an outflow trench a fall of 50cm was attained,and the holding pond filled with boulders and capped with concrete to protect from surface pollution. A small concrete  basin was built under the flow pipe to collect the overflow. We were able to have a simple inauguration ceremony the day before we left.
The quality of the water will be greatly improved but not the quantity, although by stoppering or eventually a tap, a reserve of several 100 litres can de accumulated overnight. it is still far from enough for the local demand as the village pump is still not functioning.
Cutting the fallen tree cleared the path
Cutting the fallen tree cleared the path
Improved access across the marsh
Improved access across the marsh
Moise pouring the second dam
Moise pouring the second dam
Martin and village representat.- 1st drum filled
Martin and village representat.- 1st drum filled

About Project Reports

Project Reports on GlobalGiving are posted directly to by Project Leaders as they are completed, generally every 3-4 months. To protect the integrity of these documents, GlobalGiving does not alter them; therefore you may find some language or formatting issues.

If you donate to this project or have donated to this project, you will get an e-mail when this project posts a report. You can also subscribe for reports via e-mail without donating.

Get Reports via Email

We'll only email you new reports and updates about this project.

Organization Information

Global Music Exchange

Location: Bath, Avon - United Kingdom
Website: http:/​/​
Global Music Exchange
Project Leader:
Martin Cradick
Bath, Somerset United Kingdom

Retired Project!

This project is no longer accepting donations.

Still want to help?

Find another project in Cameroon or in Health that needs your help.
Find a Project

Learn more about GlobalGiving

Teenage Science Students
Vetting +
Due Diligence


Woman Holding a Gift Card
Gift Cards

Young Girl with a Bicycle

Sign up for the GlobalGiving Newsletter

WARNING: Javascript is currently disabled or is not available in your browser. GlobalGiving makes extensive use of Javascript and will not function properly with Javascript disabled. Please enable Javascript and refresh this page.