Ecuador Clean Water Supply

 
$8,585
$21,415
Raised
Remaining
Oct 18, 2010

Design Phase

2010 Visit
2010 Visit

A site visit was scheduled between September 1st to 12th by CMU students and EWB-Pitt professional members to finalize the design phase.  A complete Design Report will be submitted to the Nationals EWB for review and approval by November 15th, 2010.

The EWB project members have been divided into six sub-teams.  Each team is specifically targeting the following aspects of the design:

 

  1. Pumping details (staged).
  2. Intake Structure at source.
  3. Piping and Distribution system.
  4. Storage Tank.
  5. Electrical and energy requirements.
  6. Community Education - long term sustainability.

Upon approval of the proposed design, an implementation trip is planned in January and April/May 2011. 

Jun 10, 2010

Tingo Pucara

A second trip to Tingo Pucara was taken in August 2009 to implement rain catchments system was installed at the Hostel and the Community Center. Additionally, ceramic filters were introduced to the community to treat and disinfect their water. Educational information regarding sanitation and hygiene was shared with the community members.

Also, researched lots of energy alternatives: solar, wind, micro-hydro turbine, grid power, diesel motors fro pumping the water from the source to the village.

Currently, the EWB Team for this project is simultaneously working in smaller individual teams. The subset of teams is as follows: Education, energy, Pumping, Sanitation, Financing, Disinfection, Empowerment/Development and Fundraising.

Wee are in the process of pnning an implementation trip sometime late this summer. Both CMU and University of Pittsburgh students are actively designing the water collection system along with sanitary options.

Details will be posted once the Nationals EWB approves the design of the proposed project.


Attachments:

About Project Reports

Project Reports on GlobalGiving are posted directly to globalgiving.org by Project Leaders as they are completed, generally every 3-4 months. To protect the integrity of these documents, GlobalGiving does not alter them; therefore you may find some language or formatting issues.

If you donate to this project or have donated to this project, you will get an e-mail when this project posts a report. You can also subscribe for reports via e-mail without donating or by subscribing to this project's RSS feed.

Retired Project

This project is no longer accepting donations.

Still want to help?
Find another project in Ecuador or in Children that needs your help.

Project Leader

Bharati Vajjhala

Staff
Pittsburgh, pennsylvania United States

Where is this project located?

Map of Ecuador Clean Water Supply