WORKPLAN FOR REPAIR OF MILLING MACHINE AND CONSTRUCTION OF WELL FOR AHINKOFI PALM KERNEL OIL ASSOCIATION
14th to 18th February, 2011: Completion of electrical works
15th to ---------- February, 2011: Drilling of well
21st to 25th February, 2011: Installation of milling machine
15th March, 2011: Commissioning of...