Kitoola Project Update: November 30, 2012

Kitoola November 12
Kitoola November 12

1. Project Status

Green. The project is running on time and on budget. Yofafo staff on the ground have been happy with the progress, and with the quality of the work so far. It compares favourably with previous classroom constructions. The contract labourers have been working well, however see (Issues) below. The students and villagers have been very excited to see their new classroom going up!

2. Activities:

The construction of the classroom began in the first week of November. A previous project, funded by individual volunteers, had already seen the construction of the concrete footings and floor, and the purchase of bricks. The scope of this project is to complete the classroom block to a finished state.

The brickwork was completed to roof height on November 12 by contracted bricklayers. The next 2 weeks saw the construction of the ring beam (a concrete beam which sits on top of the perimeter brick wall and encircles the building), and also the construction of the reinforced concrete posts for the verandah supports. The 2 photos below show the progress as of November 30.

3. Expenses to date:

$915 USD (2,445,500 UGX / Ugandan Shillings) had been spent by November 22  on materials and labour.

Purchased on 22/11/12 from Luyima Investments
Reo12mm bars (13 pcs): 325,000
Nails 4" (5 kgs): 25,000
Hoop Iron (1 roll): 40,000
Nails 3" (2 kgs): 10,000
Nails 6" (5 kgs): 25,000
Total: 425,000
Purchased on 15/11/12 from Luyima Investments
Reo 12mm bars (24 pcs): 600,000
R-6mm rings (20 pcs): 70,000 
Binding Wire (6 kgs): 42,000
Nails 2" (2 kgs): 12,000
Nails 3" (3 kgs): 15,000
Nails 4" (3 kgs): 15,000
Ventilators (105 pcs): 31,500
Cement (15 bags): 420,000
Total: 1,205,500 
Additional Purchases from various suppliers 
Sand: 240,000
Sand (second supply): 150,000
Engineer: 300,000
2 Bags of Cement: 50,000
3 Iron bars: 75,000
Total: 815,000
Grand Total: 2,445,500 UGX

4. Next Activities:

During December, the roofing work will begin. This will involve the purchase and construction on site of of timber roofing trusses, roofing iron, guttering and spouting, and payment of roofers and labourers.

Following the completion of the roofing, the building will be fitted out and finished:

  • Doors and locks
  • Student and teacher desks
  • Blackboards
  • Cupboards
  • The walls will be plastered
  • Some paintwork

It is expected that the classroom will be ready for use by January 31.

5 Issues

The lead engineer/builder is also working on other sites. Yofafo has found that has sometimes been not available when needed. It has been raised as a risk thst needs to be monitored. It has so far not affected the schedule. No other issues have been reported.

Kitoola November 27
Kitoola November 27

Links:

Comments:

About Project Reports

Project Reports on GlobalGiving are posted directly to globalgiving.org by Project Leaders as they are completed, generally every 3-4 months. To protect the integrity of these documents, GlobalGiving does not alter them; therefore you may find some language or formatting issues.

If you donate to this project or have donated to this project, you will get an e-mail when this project posts a report. You can also subscribe for reports via e-mail without donating or by subscribing to this project's RSS feed.

Funded

Combined with other sources of funding, this project raised enough money to fund the outlined activities and is no longer accepting donations.

Still want to help?
Find another project in Uganda or in Education that needs your help.

Organization

Project Leader

Valence Lutaisire

Kampala, Uganda

Where is this project located?

Map of Build Classrooms for Primary Students in Uganda